Teguh Fabrication
Request a quotation

Industrial

Pasir Gudang Pipe Rack

A 240 m two-tier pipe rack with access platforms and cat ladders for a plant expansion, galvanised throughout for a coastal industrial site.

Sector
Industrial
Location
Pasir Gudang, Johor
Year
2024
Steel
540 tonnes
Scope
Two-tier pipe rack, platforms and ladders
Client
Chemical plant operator
Duration
20 weeks
Isometric render of a long two-tier steel pipe rack carrying coloured pipelines beside a storage tank

Overview

Pipe racks leave no room for error: every bent has to land on its foundation bolts and every tier has to line up for the piping contractor. We surveyed the as-built foundations before fabrication and adjusted the base plates to suit.

The rack was erected in a working plant under the operator's permit-to-work system, with zero lost-time incidents over 20 weeks.

Finishes specified

  • Hot-dip galvanised
  • Structural steel S355
  • The rack carrying process and utility lines
    The rack carrying process and utility lines
  • The rack from the tank farm side
    The rack from the tank farm side
  • Rack bents beside the storage tank
    Rack bents beside the storage tank

Planning something similar?

Send your drawings and specification. We acknowledge within one working day and return an itemised quotation, usually within five.

Chat on WhatsApp